A. Upon receipt of a complete and satisfactory conclusive binding site plan application, copies of the record of survey for the binding site plan will be distributed for review and comment to the following offices.

1. Development Engineering

2. Fire Department

3. Grant County Assessor

4. Grant County Auditor

B. All comments shall be made to the Community Development Director within fourteen (14) days after the record of survey is distributed for review.

C. If the binding site plan is found to be unacceptable, a letter shall be mailed to the applicant within twenty (20) days of receipt of the application. (Ord. 2576, 7/27/10; Ord. 2293, 3/27/07)